( FR ) The Actual Costs ( AC ) to date are $ 1 2 , 0 0 0 and the Budget at Completion (

(FR) The Actual Costs (AC) to date are $12,000 and the Budget at Completion (BAC) for a project is $60,000. The Earned Value (EV) is $9,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $54,000. What is the Estimate at Completion (EAC) for the project?
Correct Answer
a)
$66,000
b)
$72,000
Incorrect Response
c)
$80,000
d)
$63,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these General Management questions

Question

Question 1 (a2) What is the reaction force Dx in [N]?

Answered: 1 week ago