Freddie and Jason have just opened the Texas Toothpick, a chain-saw sharpening and repair service located on Elm Street. The Texas Toothpick promises same-week repair

  • Freddie and Jason have just opened the Texas Toothpick, a chain-saw sharpening and repair service located on Elm Street. The Texas Toothpick promises same-week repair service. Freddie and Jason are concerned that a projected dramatic increase in demand as the end of October nears will cause service to deteriorate. Freddie and Jason have had difficulty attracting employees, so they are the only workers available to complete the work.
  • Safety considerations require that they each work no more than 40 hours per week. The first chain-saw sharpening and repair required 7 hours of work, and an 80 percent learning curve is anticipated.
  •  
  • Week                                      Units               Cumulative Units
  • October 2–6                            8                                  8
  • October 9–13                          19                                27
  • October 16–20                        10                                37
  • October 23–27                        27                                64
  • a.  How many total hours are required to complete 64 chain saws?(0.5pt)
  • b.  How many hours of work are required for the week ending on Friday the 13th? (1pt)
  • c.  Will Freddie and Jason be able to keep their same week service promise during their busiest week just before Halloween?(2pts)

Step by Step Solution

3.49 Rating (152 Votes )

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman

12th edition

134741064, 9780273766834, 027376683X, 9780273766940, 273766945, 9780273766841, 273766848, 978-0134741062

More Books

Students also viewed these Accounting questions

Question

6. Which processes should SPC be applied to?

Answered: 1 week ago