Fremont Corporation cost control report is shown below for the month ending June 30:
Machine hours: actual 42,000 / budgeted 40,000
Direct labor wages: actual $90,900 / budgeted $88,000 / variance $2,900 U
Supplies: actual $28,800 / budgeted $26,000 / variance $2,800 U
Maintenance: actual $25,300 / budgeted $22,900 / variance $2,400 U
Utilities: actual $23,000 / budgeted $21,700 / variance $1,300 U
Supervision: actual $56,000 / budgeted $56,000
Depreciation: actual $97,000 / budgeted $97,000
*Direct labor and supplies are variable costs. Supervision and depreciation are fixed costs. Maintenance and utilities are mixed costs. The fixed component of the budgeted maintenance cost is $18,100. The fixed component of the budgeted utilities cost is $14,300
1) complete the performance report
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started