From the following information, calculate labour cost variance, labour rate variance, Labour efficiency variance and labour yield variance and verify your answer. Standard Actual Output:
From the following information, calculate labour cost variance, labour rate variance, Labour efficiency variance and labour yield variance and verify your answer.
Standard Actual
Output: 1,000 units Actual output: 1,200 units
Rate of payment: Sh.6 per unit Wages paid: Sh.8,000
Time taken: 50 hours. Time taken: 40 hours