From the following information, compute the early, late, and slack times for each activity. Identify the critical activities. ID Task Duration Predecessor Additional Lag Relationships
From the following information, compute the early, late, and slack times for each activity. Identify the critical activities.
ID | Task | Duration | Predecessor | Additional Lag Relationships | Lag | |
A | Design | 8 | ||||
B | Order Parts | 3 | A | Start-start A to B | 6 | |
C | Code Software | 8 | A | |||
D | Assemble | 3 | B | Finish-start B to D | 4 | |
E | Debug | 3 | C | Start-start C to E Finish-finish C to E | 3 2 | |
F | Install | 4 | E, D |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started