Fuller Company builds swimming pools. Fuller budgets that they will build 13 pools during the month of April at a price of $20324 per pool.
Fuller Company builds swimming pools. Fuller budgets that they will build 13 pools during the month of April at a price of $20324 per pool. Actual pools built by Fuller during April were 16 pools at a price of $20764 per pool. What is the Sales Volume Variance for April? If the variance is unfavorable, use a negative sign right before the number with no space in between.