Question

1 Approved Answer

Geary Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $633000 is estimated to result in

Geary Machine Shop is considering a 4-year project to improve its production efficiency. Buying a new machine press for $633000 is estimated to result in $170000 in annual pretax cost savings. The press falls in the MACRS five-year class (Refer to the MACRS table on page 277), and it will have a salvage value at the end of the project of $93000. The press also requires an initial investment in spare parts inventory of $71000, along with an additional $5400 in inventory for each succeeding year of the project. If the shop's tax rate is 0.31 and its discount rate is 0.09, what is the total cash flow in year 4? (Do not round your intermediate calculations.)

(Make sure you enter the number with the appropriate +/- sign)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Multinational Business Finance

Authors: David Eiteman, Arthur Stonehill, Michael Moffett

15th Global Edition

129227008X, 9781292270081

More Books

Students also viewed these Finance questions

Question

Pick a company and explain whats helping or hurting their credit

Answered: 1 week ago