Question
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $969,600 is estimated to result in
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $969,600 is estimated to result in $323,200 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $141,400. The press also requires an initial investment in spare parts inventory of $40,400, along with an additional $6,060 in inventory for each succeeding year of the project. |
Required : |
If the shop's tax rate is 30 percent and its discount rate is 12 percent, what is the NPV for this project? (Do not round your intermediate calculations.) |
That's all information, thank you
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started