Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Genuine Spice Inc. began operations on January 1 of the current year. The company produces 8 - ounce bottles of hand and body lotion called

Genuine Spice Inc. began operations on January 1 of the current year. The company produces 8-ounce bottles of hand and body lotion called Eternal Beauty. The lotion is sold wholesale in 12-bottle cases for $100 per case. There is a selling commission of $20 per case. The January direct materials, direct labor, and factory overhead costs are as follows:
DIRECT MATERIALS
Cost Behavior Units per Case Cost per Unit Cost per Case
Cream base Variable 100 ozs. $0.02 $2.00
Natural oils Variable 30 ozs. 0.309.00
Bottle (8-oz.) Variable 12 bottles 0.506.00
$17.00
DIRECT LABOR
Department Cost Behavior Time per Case Labor Rate per Hour Cost per Case
Mixing Variable 20 min. $18.00 $6.00
Filling Variable 514.401.20
25 min. $7.20
FACTORY OVERHEAD
Cost Behavior Total Cost
Utilities Mixed $600
Facility lease Fixed 14,000
Equipment depreciation Fixed 4,300
Supplies Fixed 660
$19,560
Part ABreak-Even Analysis
The management of Genuine Spice Inc. wishes to determine the number of cases required to break even per month. The utilities cost, which is part of factory overhead, is a mixed cost. The following information was gathered from the first six months of operation regarding this cost:
Month
Case Production
Utility Total Cost
January 500 $600
February 800660
March 1,200740
April 1,100720
May 950690
June 1,025705
Required-Part A:
1. Determine the fixed and variable portions of the utility cost using the high-low method.
2. Determine the contribution margin per case.
3. Determine the fixed costs per month, including the utility fixed cost from part (1).
4. Determine the break-even number of cases per month.
Part BAugust Budgets
During July of the current year, the management of Genuine Spice Inc. asked the controller to prepare August manufacturing and income statement budgets. Demand was expected to be 1,500 cases at $100 per case for August. Inventory planning information is provided as follows:
Finished Goods Inventory:
Cases
Cost
Estimated finished goods inventory, August 1300 $12,000
Desired finished goods inventory, August 311757,000
Materials Inventory:
Cream Base
Oils
Bottles
(ozs.)
(ozs.)
(bottles)
Estimated materials inventory, August 1250290600
Desired materials inventory, August 311,000360240
There was negligible work in process inventory assumed for either the beginning or end of the month; thus, none was assumed. In addition, there was no change in the cost per unit or estimated units per case operating data from January.
Required-Part B:
5. Prepare the August production budget.
6. Prepare the August direct materials purchases budget.
7. Prepare the August direct labor budget.
8. Prepare the August factory overhead budget.
9. Prepare the August budgeted income statement, including selling expenses.
Part CAugust Variance Analysis
During September of the current year, the controller was asked to perform variance analyses for August. The January operating data provided the standard prices, rates, times, and quantities per case. There were 1,500 actual cases produced during August, which was 250 more cases than planned at the beginning of the month. Actual data for August were as follows:
Actual Direct Materials
Price per Unit
Quantity per Case
Cream base $0.016 per oz.102 ozs.
Natural oils $0.32 per oz.31 ozs.
Bottle (8-oz.) $0.42 per bottle 12.5 bottles
Actual Direct
Actual Direct Labor
Labor Rate
Time per Case
Mixing $18.2019.50 min.
Filling 14.005.60 min.
Actual variable overhead $305.00
Normal volume 1,600 cases
The prices of the materials were different than standard due to fluctuations in market prices. The standard quantity of materials used per case was an ideal standard. The Mixing Department used a higher grade labor classification during the month, thus causing the actual labor rate to exceed standard. The Filling Department used a lower grade labor classification during the month, thus causing the actual labor rate to be less than standard.
Required-Part C:
10. Determine and interpret the direct materials price and quantity variances for the three materials.
11. Determine and interpret the direct labor rate and time variances for the two departments.
12. Determine and interpret the factory overhead controllable variance.
13. Determine and interpret the factory overhead volume variance.
14. Why are the standard direct labor and direct materials costs in the calculations for parts (10) and (11) based on the actual 1,500-case production volume rather than the planned 1,375 cases of production used in the budgets for parts (6) and (7)?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting An Integrated Statements Approach

Authors: Jonathan E. Duchac, James M. Reeve, Carl S. Warren

2nd Edition

324312113, 978-0324312119

Students also viewed these Accounting questions