George is the manager of a small construction company engaged in foundation work. The vertical walls are to be formed immediately following the foundation slab. You have allowed 24 hours between the slab and the start of the vertical work to allow the concrete to cure to an adequate bearing strength. Which of the following is this an example of: Select one: Lead Lag Soft Logic Finish-to-Start relationship