Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Getting the HUMS project off the ground deliver the required assurance processes. - HUMS are able to improve other aspects of the project's business, in

image text in transcribed
image text in transcribed
Getting the HUMS project off the ground deliver the required assurance processes. - HUMS are able to improve other aspects of the project's business, in particular, stakeholder relationships through more accurate planning associated with forecast delivery schedules Health and Usage Monitoring Systems (HUMS) is a technology that uses vibration-based drive-train monitoring and costs. Ongoing Risk Focus The HUMS project continued to embed risk management culture across the team to accurately determine a helicopter's mechanical health and maintenance requirements. Through its implement and as the project progressed, continually reassessed deliverables to ensure that all possible risks and opportuni- tation, operators can increase aircraft availability by reducing downtime for maintenance flights and forward ties were considered and planned for. To support them, Risk Decisions conducted monthly audits with ongoing plan routine repairs. Civilian oil and gas engineers first developed HUMS to improve the safety of helicopters op- coaching. "Risk is now a key element of the management of the HUMS Project and will continue to remain an erating in the hostile environment of the North Sea. The UK Ministry of Defence quickly realised the safety and important element in our decision making," says Commander Mark Deaney, HUMS Project Team Leader. Source: operational cost benefits that could be achieved through embracing this new technology and started their own https://www.riskdecisions.com/risk-management-case-studies/hums-project-delivery-case-study/ development programmes. The HUMS Project Team were tasked with getting Initial and Main Gate funding ap- proval for the technology through the Investment Advisory Board (IAB). When they got the go ahead, the project QUESTION 1 (20 Marks) By referring to the benefits of project risk management that you have studied, appraise team relocated from Bristol to RNAS Yeovilton, so that HUMS could be applied to military helicopter platforms. the benefits derived by the HUMS project who have adopted prudent project risk management. QUESTION 2 The The Challenge The project's relocation and subsequent changes in personnel resulted in the loss of much, if not primary output of risk identification is the risk register. Design a risk register for the project in the case study. all, of the established risk management practice. Nobody held the position of dedicated 'Risk Manager' and the Ensure that at least five (5) relevant risks are recorded on the register. Thereafter, discuss each risk in detail team of 12 were attempting to handle multiple disparate risk registers without risk impact assessments or miti- gation actions. Finally, the fragile relationship between the struggling project and key stakeholders disintegrated as Cost and Time criteria for the project overran. Commander Mark Deaney took over as Project Leader, inherit- ing the challenge of submitting a Review Note and reabaselining the project. Commander Deaney had aspira- End of document tions to embed best risk management practice as part of the IPT's daily business, having seen its benefit on the Harrier GR9 project, and specifically, his aim was to reach level 3 risk maturity. This was the point at which the project approached Risk Decisions to help them meet the challenge. The Risk Decisions' Solution Risk Decisions reviewed the project's existing risk management strategy, plan and process and worked with them to develop a roadmap for improvements that included achieving cultural and behavioural 'buy in' from the team. A tailored programme of risk consultancy, training and workshops was recommended to help the project embed sustaina- ble risk management to achieve their longer-term aspirations. To support the adoption of best risk management practice, Risk Decisions provided their Predict! risk management software tools giving the team a framework for identifying and analysing risks, and planning and managing mitigation and fall-back actions. The toolset also pro- vided the team with the ability to do complex risk and uncertainty analysis modelling for time and cost. Predict! Risk Reporting capability then allowed decision makers to prioritise the management of risks and issues and sub- sequently inform them of any current or future resource requirements. The Benefits Risk Decisions worked closely with team members to ensure that they understood the rationale behind effective and sustainable risk management and were enabled with the tools and skill sets to perform risk analysis. As a result the team achieved the following benefits: - The HUMS project achieved level 3 maturity and successfully submitted the project Review Note to the IAB. - The project improved their understanding of the project cost drivers and imple- mented a process for managing the overall project costs and mitigating risk. - All the stakeholders have a good visibility of risks to the project and their associated priority and a central repository to handle their risks. - The team have the confidence to perform risk management effectively against their target projects and are able to

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Tourism Concepts And Practices

Authors: John R Walker, Josielyn T Walker

1st Edition

0138142459, 9780138142452

More Books

Students also viewed these General Management questions

Question

=+b) Cut the runs to 8 by testing only in hot water.

Answered: 1 week ago

Question

A greater tendency to create winwin situations.

Answered: 1 week ago

Question

Improving creative problem-solving ability.

Answered: 1 week ago