Give 2 common reasons why scope creep occurs? Give 2 examples of what project managers can do to control Scope Creep. Reporting performance keeps stakeholders
Give 2 common reasons why scope creep occurs?
Give 2 examples of what project managers can do to control Scope Creep.
Reporting performance keeps stakeholders informed about how resources are being used to achieve project objectives.
Describe the three types of project reporting that a project manager would commonly use to inform the stakeholders of project progress.
You have a project where Cost Performance Indicator (CPI) of .80 which means we are spending more money than we should spend. And we have Schedule Performance Indicator (SPI) of 1.20, which means we are ahead of schedule. Do you think we should be worried because we are spending more than budgeted money? Explain your answer
Step by Step Solution
3.42 Rating (158 Votes )
There are 3 Steps involved in it
Step: 1
Two common reasons why scope creep occurs are Poor initial project planning When project requirements and objectives are not clearly defined and documented from the beginning it becomes easier for add...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started