Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

give me the answer in picture 2- lets say the marketing team is producing a new interactive blog post. Here are some tasks that might

give me the answer in picture

2- lets say the marketing team is producing a new interactive blog post. Here are some tasks that might be in the work breakdown structure: (a) draw a network diagram, (b) determine the critical path and project completion time, and (c) determine the float for all activities not on thecritical path.

task id :A-task:Create outline-duration(days):1 task id :B-task:write draft-duration(days):5 task id :C-task:Edit and create final draft-duration(days):2 task id :D-task:Design post visuals-duration(days):4 task id :E-task:Add animations to visuals-duration(days):2 task id :F-task:Upload post-duration(days):1

The network digram from star the task until finish

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Forensic Accounting And Fraud Investigation For Non-Experts

Authors: Stephen Pedneault, Frank Rudewicz, Howard Silverstone, Michael Sheetz

3rd Edition

0470879599, 9780470879597

More Books

Students also viewed these Accounting questions