Question

1 Approved Answer

Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 1 4 4 2

Given a simple project illustrated in the following table Activity Immediate Predecessors Time (weeks) 1 - 2 2 1 3 3 1 4 4 2 2 5 3, 4 2 Assume that "Activity 1" actually finished at 3 weeks, "Activity 2" actually finished at 7 weeks, and "Activity 3" actually finished at 6 weeks. Given the actual project progress, what is the ES (earliest start time) of "Activity 5

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these General Management questions