Question

1 Approved Answer

Given below is the time-cost trade-off data for a small project. Assume the Indirect Cost is SR100/day. Calculate the optimal project duration. Activity Predecessors

Given below is the time-cost trade-off data for a small project. Assume the Indirect Cost is SR100/day. Calculate the optimal project duration. Activity Predecessors Normal Crash Duration D. Cost Duration D. Cost w. days Slope SR w. days SR 4 100 300 100 B 3 200 200 , 2. 50 100 50 D , 3. 100 2. 300 200 4 150 400 83.3 F , D 4. 250 400 50 G D, E 300 00 \00 H. F, G 3. 200 300

Step by Step Solution

3.43 Rating (159 Votes )

There are 3 Steps involved in it

Step: 1

1 STEP1 NORMAL DURATION DURATION 23 DAYS 2 STEP2 CRASH DURATION 3 OPTIMAL DURATION 4 STEP4 SUMMARY ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting Information For Decisions

Authors: Robert w Ingram, Thomas L Albright

6th Edition

9780324313413, 324672705, 324313411, 978-0324672701

More Books

Students also viewed these Accounting questions

Question

Define induction and what are its objectives ?

Answered: 1 week ago

Question

Discuss the techniques of job analysis.

Answered: 1 week ago

Question

How do we do subnetting in IPv6?Explain with a suitable example.

Answered: 1 week ago

Question

Explain the guideline for job description.

Answered: 1 week ago

Question

What is job description ? State the uses of job description.

Answered: 1 week ago

Question

Why do workers sometimes resent time studies?

Answered: 1 week ago