Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? Budget Actual Budget Earned

image text in transcribed
Given PV (BCWS) equals $1,500,000; EV (BCWP) equals $1,575,000; AV (ACWP) equals $1,490.000. Which of the following is a true statement? Budget Actual Budget Earned Percent Account Code UOM Quantity Quantity PV EV Complete Total To-Date 03110 Formwork SF 4,000 3,000 6,000 03210 Rebar Ton 10 6 900 03310 Place & Finish CY 800 640 1,600 Subtotal Slabs at grade a. The project is over budget and behind schedule b. The project is under budget and ahead of schedule C. The project is over budget and ahead of schedule . d. The project is under budget and behind schedule

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foodservice Management Principles And Practices

Authors: June Payne Palacio, Monica Theis

13th Edition

0133801101, 9780133801101

More Books

Students also viewed these General Management questions

Question

1. To generate a discussion on the concept of roles

Answered: 1 week ago

Question

6. What information processes operate in communication situations?

Answered: 1 week ago