Given that the labor productivity rate is 0.5 labor hours/cy and the wage rate is $15.25/hour, determine the labor cost if there are 1,628.1cf of
Given that the labor productivity rate is 0.5 labor hours/cy and the wage rate is $15.25/hour, determine the labor cost if there are 1,628.1cf of concrete to be poured.
12414.26 |
459.79 |
1379.28 |
578.9 |