Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Given the activities whose sequence is described by the following table i) Draw the appropriate activity-on-arrow (AOA) network diagram neatly. Calculate ES, EF, LS,
Given the activities whose sequence is described by the following table i) Draw the appropriate activity-on-arrow (AOA) network diagram neatly. Calculate ES, EF, LS, LF and slack for each activity. ii) iii) Identify the critical activities and calculate the project completion time. iv) Determine the probability (In Percentage) that the project will be complete by the 37th day. Activity A B C D E F G H I K Immediate Predecessor(s) - A B C B C D. E G F, H I F Time t Variance (days) 7 5 5 3 6 11 4 3 5 7 10 1 0.25 0.15 0.75 0.5 0.1 0.25 0.2 1 0.2 0.4
Step by Step Solution
★★★★★
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Answer Lets start by drawing the ActivityonArrow AOA network diagram A7 B5 E6 J7 K10 C5 F11 I5 D3 G4 ...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started