Question

1 Approved Answer

Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI. Consider

Given the below chart, calculate the SV, CPI, SPI, EAC (typical), EAC (atypical/conservative), VAC (CPI only), VAC (CPI and SPI), and the original TCPI.

Consider it is currently at the end of Month 2. This implies that task 6 was planned to be completed but was not started. Be sure to show all of your work.

Planned Schedule and Budget

Actual Cost

Task

Month 1

Month 2

Month 3

1

$4,000

$6,000

2

$1,000

$4,000

3

$3,000

$4,000

4

$5,000

$1,000

5

$5,000

$4,000

6

$3,000

7

$1,000

8

$2,000

9

$4,000

Total

$8,000

$13,000

$7,000

$19,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Portfolio Of Marketing Audits Company Self Assessment Audits

Authors: David Crosby

1st Edition

1902433157, 978-1902433158

More Books

Students also viewed these Accounting questions

Question

=+b) What would the mean of the sampling distribution be?

Answered: 1 week ago

Question

Identify the cause of a performance problem. page 363

Answered: 1 week ago