Given the BOM and MPS for end items A and B shown below, complete the MRP schedules for A , B , C , D
Given the BOM and MPS for end items A and B shown below, complete the MRP schedules for A B C D and E
A B C for A D for A E for C C for B E for B E for C
Weeks
Units
MPS
Week Week Week Week Week Week Week Week
Item A
Item B
Item A B C D E
Lot Size Rule LL LL FOQ FOQ LL
Safety Stock
Beginning Inventory
Order quantity
Order quantity
Required:
Note: Use cells A to I from the given information to complete this question. Leave no cells blank be certain to enter wherever required.
MRP Record Part Name: Item A
Week Week Week Week Week Week Week Week
Gross requirements
Scheduled receipts
Available inventory
Net requirements
Planned order receipts
Planned order releases
MRP Record Part Name: Item B
Week Week Week Week Week Week Week Week
Gross requirements
Scheduled receipts
Available inventory
Net requirements
Planned order receipts
Planned order releases
MRP Record Part Name: Item C
Week Week Week Week Week Week Week Week
Gross requirements
Scheduled receipts
Available inventory
Net requirements
Planned order receipts
Planned order releases
MRP Record Part Name: Item D
Week Week Week Week Week Week Week Week
Gross requirements
Scheduled receipts
Available inventory
Net requirements
Planned order receipts
Planned order releases
MRP Record Part Name: Item E
Week Week Week Week Week Week Week Week
Gross requirements
Scheduled receipts
Available inventory
Net requirements
Planned order receipts
Planned order releases
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started