Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Given the case study below: 1. Determine a risk statement for each risk with the project and/or business impact of each of a risk? Hint:

image text in transcribed

Given the case study below:

1. Determine a risk statement for each risk with the project and/or business impact of each of a risk? Hint: You must determine the project and/or business impact based on the schedule when the risk occurs.

2. Of the four proposals, can you eliminate any of them? If so, which ones and why? Hint: Look at the schedule duration of each proposal.

3. Based on the viable mitigation proposals, show the expected monetary value (EMV) and range of the expected net profit and loss for each viable proposal?

4. What would you recommend to the president based on question #3? Explain how you adjust the project schedule and budget baseline for actively managing risks and how you create the risk reserve for the schedule and budget as a contingency? Hint: the project schedule baseline is the duration in weeks that project has allowed to complete the project and project cost baseline is amount to do the work plus $300,000 net profit.

Case Study:

image text in transcribedimage text in transcribedimage text in transcribed
The Sharon Construction Corporation has been awarded a contract for the construction of a 20,000-seat stadium. The construction starts on Monday, February 15, 2016 and must be completed within 52 weeks. A penalty clause of $15,000 per week for each full or partial of delay beyond this date was written into the contract. Jim Brown, the president of the company, called a planning meeting. In the meeting he expressed great satisfaction at obtaining the contract and revealed that the company could net as much as $300,000 on the project. He was confident that the project could be completed on time with an allowance made for the usual delays anticipated in such a large project. Bonnie Green, the director of personnel, agreed that in a normal year only slight delays might develop due to a shortage of labor. However, she reminded the president that for such a large project, the company would have to use unionized employees and that the construction industry labor agreements were to expire on November 27. Past experience indicated a fifty-fifty chance of a strike. Jim Brown agreed that a strike might cause a problem. Unfortunately, there was no way to change the contract. He inquired about the prospective length of a strike. Bonnie figured that such a strike would last either eight weeks (70 percent chance) or possibly 12 weeks (30 percent chance). Jim was not pleased with these prospects. However, before he had a chance to discuss contingency plans he was interrupted by Jack White, the vice-president for engineering. Jack commented that a colder December than had been assumed was now being predicted. This factor had not been taken into consideration during earlier estimates since previous forecasts called for milder weather. Concrete pouring in December might thus require in one out of every three cases (depending on the temperature) special heating that costs $500 per week. This additional information did not please Jim at all. The chances for delay were mounting. And an overhead expense of $500 per week would be incurred in case of any delay that exceeds the baseline schedule as defined in Appendix. The technical details of the project are given in the appendix to this case. The management team was asked to consider alternatives for coping with the situation. At the end of the week, four proposals were submitted: 1. Expedite the pouring of seat gallery supports. This would cost $20,000 and cut the duration of the activity to six weeks. 2. Put a double shift on the filling of the field. A cost of $10,000 would result in a five-week time reduction. 3. The roof is very important since it precedes several activities. The use of three shifts and some overtime could cut six weeks off the roofing at an additional cost of only $9,000. 4. Do nothingAppendix: Technical Details of the Stadium The stadium is an indoor structure with a seating capacity of 20,000. The project begins with clearing the site, an activity that lasts eight weeks. Once the site is clear, the work can start simultaneously on the structure itself and on the field. The work in the field involves subsurface drainage which lasts eight weeks, followed by filling for the playing field and track. Only with the completion of the filling (14 weeks) can the installation of the artificial playing turf take place, an activity that consumes 12 weeks. The work on the structure itself starts with excavation followed by the pouring of concrete footings. Each of these activities takes four weeks. Next comes the pouring of supports for seat galleries (12 weeks), followed by erecting pre-cast galleries (13 weeks). The seats can then be poured (4 weeks) and are ready for painting. However, the painting (3 weeks) cannot begin until the dressing rooms are completed (4 weeks). The dressing rooms can be completed only after the roof is erected (8 weeks). The roof must be erected on a steel structure which takes 4 weeks to install. This activity can start only after the concrete footings are poured. Once the roof is erected, work can start simultaneously on the lights (5 weeks) and on the scoreboard and other facilities (4 weeks). Assume that there are 28 days in February and that project starts February 15, 2016, which falls on a Monday. Note: The schedule can be developed using Microsoft Project or Excel - See "Chapter 8 Sharon Case Study Template.xlex" in the Tools folder in D2L. Assume 5-day work week and calendar units are in weeks. No overtime is allowed.Start Finish Fill Field Task Name Erect Roof Pour Seats Paint Seats Excavation Instal Lights Site Clearing Pour Foorting Install Scoreboard Install Artifical Turff Erect Steel Structure Sub-Surface Drainage Erect Pre-Cast Galeries Complete Dressing Rooms Pour Seat Gallery Support 4 wks 4 wks 3 wks 4 wks 4 wks 8 wks 5 wks 4 wks 8 wks 8 wks 4 wks 0 days 0 days 13 wks 12 wks 12 wks 14 wks Duration Predecessor Slack 2/15/2016 2/22/2016 2/29/2016 1 2 3 4 3/7/ 20 16 3/14/2016 5 3/21/20 16 6 3/28/20 16 7 4/4/20 16 4/11/20 16 4/18/20 16 4/25/20 16 5/2/20 16 5/9/2016 5/16/2016 5/23/2016 5/30/2016 6/6/2016 6/13/2016 6/20/2016 6/27/2016 7/4/2016 7/11/2016 7/18/2016 7/25/20 16 8/1/2016 8/8/2016 8/15/2016 8/22/20 16 8/29/20 16 9/5/2016 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 9/12/2016 9/19/2016 9/26/2016 10/3/2016 10/10/2016 10/17/2016 10/24/20 16 10/31/2016 11/7/2016 11/14/2016 11/21/2016 11/28/2016 12/5/2016 12/12/2016 12/19/2016 12/26/2016 1/2/2017 1/9/2017 1/16/2017 1/23/2017 1/30/2017 feb 13 2017 2/6/2017

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Probability And Statistics For Engineering And The Sciences

Authors: Jay L. Devore

9th Edition

1305251806, 978-1305251809

Students also viewed these General Management questions