Question
1 Approved Answer
Given: The direct costs for a bid have been estimated at $300,000, project overhead is 10%, and company overhead is 12%. What is the total
Given: The direct costs for a bid have been estimated at $300,000, project overhead is 10%, and company overhead is 12%. What is the total bid amount before adding a markup for profit? The estimated direct costs for a bid are $300,000. Project overhead is 10%, and company overhead is 12%. What is the total bid amount before adding a markup for profit? 1. $366,000.00 2. $369,600.00 3. $384,615.38 4. $398,736.89
Step by Step Solution
There are 3 Steps involved in it
Step: 1