Question
. Given the following cash flows for four projects, calculate the net present value using a discount rate of 12% a year. What are the
. Given the following cash flows for four projects, calculate the net present value using a discount rate of 12% a year. What are the internal rates of return for the projects? Which project is the best?
Project A Project B Project C Project D
Year Income Expenditure Income Expenditure Income Expenditure Income Expenditure
0 0 18,000 0 5,000 0 24,000 0 21,000
1 2,500 0 0 10,000 2,000 10,000 0 12,000
2 13,500 6,000 0 20,000 10,000 6,000 20,000 5,000
3 18,000 0 10,000 20,000 20,000 2,000 20,000 1,000
4 9,000 2,000 30,000 10,000 30,000 2,000 30,000 0
5 5,000 0 50,000 5,000 25,000 2,000 25,000 0
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3