Given the following cost and activity observations for Smithson Company's utilities, use the high-low method to calculate Smithson's fixed costs per month. Cost Machine Hours

Given the following cost and activity observations for Smithson Company's utilities, use the high-low method to calculate Smithson's fixed costs per month.

Cost

Machine Hours

January $75,830 10,100
February 126,860 18,200
March 88,800 12,100
April 108,830 15,300

a.$12,200

b.$20,700

c.$9,800

d.$39,000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Assurance Services Plus Pearson MyLab Accounting With Pearson EText

Authors: Alvin A. Arens, Randal J. Elder, Mark S. Beasley, Chris E. Hogan

17th Global Edition

1292312106, 978-1292312101

More Books

Students also viewed these Accounting questions