Given the following data for Project M calculate the NPV of the project. Cash flow in real terms Year 1, -200. Year 2, 150, Year
Given the following data for Project M calculate the NPV of the project.
Cash flow in real terms Year 1, -200. Year 2, 150, Year 3, 120
Real discount rate = 5%
Nomial discount rate = 10%
Select one:
a.$51.70
b.$35.54
c.$45.21
d.$70.00
e.None of the above