Question
Given the following data for work packages in a PERT/Cost network at week 18: Activity Immediate Predecessors Budgeted Time (weeks) Budgeted Cost (planned) Percent Complete
Given the following data for work packages in a PERT/Cost network at week 18:
Activity | Immediate Predecessors | Budgeted Time (weeks) | Budgeted Cost (planned) | Percent Complete | Expense To Date |
A | -- | 12 | $50,000 | 100% | $48,000 |
B | -- | 8 | $20,000 | 100% | $21,000 |
C | A | 6 | $60,000 | 75% | $40,000 |
D | B | 16 | $40,000 | 50% | $25,000 |
E | C, D | 16 | $45,000 | 0% | 0 |
F | B | 28 | $80,000 | 75% | $55,000 |
Is the project currently, experiencing a cost overrun?
Ltfen birini sein:
a. The project is currently, experiencing cost overrun, the value of work= 189000, the actual cost=195000
b. The project is currently, experiencing cost overrun, the budgeted cost=295000, the value of work= 189000
c. The project is currently, experiencing cost underrun, the value of work= 195000, the actual cost=189000
d. The project is currently, experiencing cost underrun, the budgeted cost=295000, the value of work= 189000
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started