Given the following elements of a CPIF Contract, is the Government required to pay the Contractor's Final Cost of $1,100,000, assuming all the costs are
Given the following elements of a CPIF Contract, is the Government required to pay the Contractor's Final Cost of $1,100,000, assuming all the costs are reasonable, allocable and allowable?
Target Cost: $1,000,000
Target Fee: $80,000
Under Share: 90/10
Maximum Fee: $100,000
Minimum Fee: $50,000
Over Share: 70/30
O Yes
O No