Question
1 Approved Answer
Given the following information, compute the early, late, and slack times for the project network. ID Task Duration Predecessor Additional Lag Relationships Lag A Post
Given the following information, compute the early, late, and slack times for the project network.
ID | Task | Duration | Predecessor | Additional Lag Relationships | Lag | |
A | Post Signs | 5 | ||||
B | Prepare Site | 6 | A | Finish-start A to B | 11 | |
C | Lights | 6 | B | |||
D | Dig Trenches | 5 | B | |||
E | Lay Pipe | 6 | D | Start-start D to E | 3 | |
F | Back Fill | 1 | E | Start-start E to F | 1 | |
G | Pave | 2 | F | |||
H | Paint Parking Lines | 1 | G | Finish-start G to H | 1 | |
I | Signage | 3 | G | |||
J | Open Lot | 1 | C, H, I | |||
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started