Question

1 Approved Answer

Given the following information, compute the early, late, and slack times for the project network. ID Task Duration Predecessor Additional Lag Relationships Lag A Post

Given the following information, compute the early, late, and slack times for the project network.

ID Task Duration Predecessor Additional Lag Relationships Lag
A Post Signs 5
B Prepare Site 6 A Finish-start A to B 11
C Lights 6 B
D Dig Trenches 5 B
E Lay Pipe 6 D Start-start D to E 3
F Back Fill 1 E Start-start E to F 1
G Pave 2 F
H Paint Parking Lines 1 G Finish-start G to H 1
I Signage 3 G
J Open Lot 1 C, H, I

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Markets Instruments And Institutions

Authors: Anthony M. Santomero, David Babbel

2nd Edition

0072358688, 9780072358681

More Books

Students also viewed these Finance questions

Question

1 Why is job analysis important?

Answered: 1 week ago