Given the following information for a project, determine the critical path. Activity Immediate Processor Activity Time (days) A - 6 B - 8 C A,B
Given the following information for a project, determine the critical path.
Activity | Immediate Processor | Activity Time (days) |
A | - | 6 |
B | - | 8 |
C | A,B | 5 |
D | B | 4 |
E | C | 7 |
F | C,D | 3 |
G | D | 6 |
H | E,F,G | 5 |
a. | A-C-E-H | |
b. | B-C-E-H | |
c. | B-D-F-H | |
d. | B-D-G-H | |
e. | B-C-F-H |