Given the following information for Albright Company, what was the total manufacturing cost variance? Manufacturing Costs Actual Costs Standard Cost at Actual Volume Budgeted Cost
Given the following information for Albright Company, what was the total manufacturing cost variance?
Manufacturing Costs | Actual Costs | Standard Cost at Actual Volume | Budgeted Cost | |||
Direct materials | $ 80,300 | $ 76,000 | $ 71,250 | |||
Direct labor | 77,000 | 72,500 | 68,400 | |||
Factory overhead | 44,800 | 48,000 | 45,600 | |||
Total | $202,100 | $196,500 | $185,250 |
a.$3,200 unfavorable
b.$5,600 unfavorable
c.$16,850 unfavorable
d.$(5,600) favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started