Question

1 Approved Answer

Given the following information on equipment installation project at week 25 , calcualte the estimate cost at completion (EAC) ( Give your answer to the

Given the following information on equipment installation project at week 25 , calcualte the estimate cost at completion (EAC)( Give your answer to the nearest dollarand submit without the dollar sign)

Activity

Predecessors

Duration(weeks)

Budget ($)

Actual cost ($)

% Completed

A

-

6

900

1000

100

B

-

6

1200

1500

100

C

A

6

1200

1600

100

D

A

12

1800

2500

100

E

B,C

14

1400

1500

90

F

B,C,D

10

1500

750

50

G

D,E

16

800

0

0

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Options Futures And Other Derivatives

Authors: John C. Hull

3rd Edition

0131864793, 9780306457555

More Books

Students also viewed these Finance questions

Question

What is the content-level meaning?

Answered: 1 week ago