Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 c None 8 d a 7 e b 5
Given the following information regarding a project: Activity Predecessors Duration a None 3 b None 6 c None 8 d a 7 e b 5 f c 10 g c 4 h d,e,f 5 i g 6 What is the LS for activity c? 0 3 6 7 8