Given the following information, what is the master production schedule (MPS) for week 5? Opening inventory = 100 units Lot size = 200 units Forecasted
Given the following information, what is the master production schedule (MPS) for week 5? Opening inventory = 100 units Lot size = 200 units Forecasted sales: . Week 1= 150 units Week 2 100 units . Week 3 = 60 units Week 4 = 80 units - Week 5 = 140 units Note: Assume that the master scheduler wants to keep inventory levels to a minimum while still meeting all projected demand. . 200 0 100 400