Given the following PERT network 3 weeks 2 weeks 0 week 1 week QUESTION 20 Given the following PERT network 5 c Start 3 8
Given the following PERT network 3 weeks 2 weeks 0 week 1 week
QUESTION 20 Given the following PERT network 5 c Start 3 8 11 4 End 8 6 What is the slack of task G? 0 3 weeks @ 2 weeks C) O week C) I week