Given the following: Project A: CF0 = -$23,480; CF1 = $6,600; CF2 = $9,100; CF3 = $15,700 Project B: CF0 = -$19,880; CF1 = $4,120;
Given the following: Project A: CF0 = -$23,480; CF1 = $6,600; CF2 = $9,100; CF3 = $15,700 Project B: CF0 = -$19,880; CF1 = $4,120; CF2 = $8,030; CF3 = $15,080 What is the crossover rate (r)?