Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Given the following project data, draw the project network diagram, identify the critical path, and determine the completion time. Assume the project contract states

Given the following project data, draw the project network diagram, identify the critical path, and determine the completion time. Assume the project contract states that if the project is not completed by the 14th day, your firm will experience a penalty of $100 per day until the job is completed. Determine what, if any, penalty would be incurred. If you need to crash an activity, which activity would you crash first? Why? Is there a point at which it is no longer cost effective to crash activities? Activity Normal Time (days) A 4 Normal Cost ($) Crash Time (days) 2,000 3 Crash Cost ($) Immediate Predecessor(s) 2,600 None B 7 1,400 4 2,000 None C 5 1,000 4 1,700 None D 6 1,200 5 1,400 A E 3 b00 2 1,100 B LL F 11 2,500 6 3,750 C G 4 900 3 1,540 D, E H 3 600 1 1000 F, G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions