Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

Given the following project data that include a table of activities, durations in days, precedence, and costs. A field report was issued at the end

Given the following project data that include a table of activities, durations in days, precedence, and costs.

A field report was issued at the end of DAY 8 as shown. Compute the required values in the EV analysis and fill in the sky-blue blanks for activities C and E. Please, use only two decimal points in your calculations.

Planned Values

Field Report day 8

Activity

Predecessor

Duration(days)

Cost/day

Total Cost

Activity

% Complete

Incurred Cost

A

2

$300

$600

A

100%

$600

B

A

3

$400

$1,200

B

100%

$1,400

C

B

3

$400

$1,200

C

50%

$800

D

B

2

$200

$400

D

100%

$600

E

D

3

$100

$300

E

50%

$100

Activity

AC

EV

PV

CPI

CV

SPI

SV

A

B

C

D

E

1. Activity C CPI :

2. Activity C CV :

3. Activity C SPI:

4. Activity C SV:

5. Activity E CPI:

6. Activity E CV:

7. Activity E SPI:

8. Activity E SV:

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions