Question
Given the following project data that include a table of activities, durations in days, precedence, and costs. A field report was issued at the end
Given the following project data that include a table of activities, durations in days, precedence, and costs.
A field report was issued at the end of DAY 8 as shown. Compute the required values in the EV analysis and fill in the sky-blue blanks for activities C and E. Please, use only two decimal points in your calculations.
Planned Values | Field Report day 8 | |||||||
Activity | Predecessor | Duration(days) | Cost/day | Total Cost |
| Activity | % Complete | Incurred Cost |
A |
| 2 | $300 | $600 | A | 100% | $600 | |
B | A | 3 | $400 | $1,200 | B | 100% | $1,400 | |
C | B | 3 | $400 | $1,200 | C | 50% | $800 | |
D | B | 2 | $200 | $400 | D | 100% | $600 | |
E | D | 3 | $100 | $300 | E | 50% | $100 | |
Activity | AC | EV | PV | CPI | CV | SPI | SV | |
A |
|
|
|
|
|
|
| |
B |
|
|
|
|
|
|
| |
C |
|
|
|
|
|
|
| |
D |
|
|
|
|
|
|
| |
E |
|
|
|
|
|
|
|
1. Activity C CPI :
2. Activity C CV :
3. Activity C SPI:
4. Activity C SV:
5. Activity E CPI:
6. Activity E CV:
7. Activity E SPI:
8. Activity E SV:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started