Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate
Given the following project network, baseline, and status information, develop status reports for periods 2, 4, 6, 8, and complete the performance indexes table. Calculate the forecasted estimate at completion (EAC) and the forecasted variance at completion (VAC). Based on your data, what is your assessment of the current status of the project? Is it at completion?
Use the project network, baseline chart, and status report table below to answer this learning activity:
\fBudget Allocations ID Budget 1 ($000) 2 3 4 5 6 7 8 9 10 11 12 A 40 10 10 10 10 S 32 8 4 8 4 8 C 48 12 12 12 12 D 18 6 2 2 2 6 E 28 8 8 12 F 40 20 20 Total 206 18 14 18 14 20 26 22 26 2 6 20 20 Cumulative 18 32 50 64 84 110 132 158 160 166 186 206Status Reports Status Report: Ending Period 2 ($000) Task % Complete EV AC PV CV SV A 75% 25 B 50% 12 Cumulative Totals 37 Status Report: Ending Period 4 ($000) Task % Complete EV AC PV CV SVA 100% 35 B 100% 24 Cumulative Totals 59 Status Report: Ending Period 6 ($000) Task % Complete EV AC PV CV SV A 100% 35 B 100% 24 C 75% 24D 0% 0 E 50% 10 Cumulative Totals 93 Status Report: Ending Period 8 ($000) Task % Complete EV AC PV CV SV A 100% 35 B 100% 24 C 100% 32D 33% 20 E 100% 20 Cumulative Totals 131 Performance Indexes Summary Period EV AC PV SPI CPI PCIB 2 4 68 EAC = VAC =Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started