Question
1 Approved Answer
Given the following project network, baseline, and status information, develop status reports for periods 14 and complete the project summary graph (or a similar one).
Given the following project network, baseline, and status information, develop status reports for periods 14 and complete the project summary graph (or a similar one). Report the final SV, CV, CPI, and PCIB. Based on your data, what is your assessment of the current status of the project? At completion?
0 A 4 1 1 1 4 5 0B5 00 0 5 5 ID Budget ($000) 40 32 48 18 28 40 206 A B D E F Total Cumulative 0 4 2 6 4 5 D 0 5 5 5 E 2 7 3 8 2 10 10 0 10 8 2 10 3 4 18 14 18 32 50 1 2 10 10 10 10 8 4 8 4 18 14 10 F 12 0 0 10 2 12 8 9 5 00 6 7 8 12 12 12 12 8 8 12 20 20 20 26 22 26 2 6 20 20 64 84 110 132 158 160 166 186 206 LEGEND 6 ES ID EF SL SL LS DUR LF 10 11 12 Status Report: Ending Period 2 Task A B Cumulative Totals Status Report: Ending Period 4 Task A B Cumulative Totals Status Report: Ending Perlod 6 Task A B D E Cumulative Totals Status Report: Ending Period 8 Task A B D E Cumulative Totals Performance Indexes Summary Period EV 2 4 6 8 EAC, % Complete 75% 50% % Complete 100% 100% % Complote 100% 100% 75% 0% 50% % Complote 100% 100% 100% 33% 100% AC VAC, EV - EV | | | | - ||||| EV PV AC 25 12 37 AC 35 24 59 AC 35 24 24 0 10 93 AC 35 24 32 20 20 131 SPI PV PV PV - PV 5|||| CV ($000) ($000) 5||| CV SV ($000) SV SV ($000) SV PCIB 0 A 4 1 1 1 4 5 0B5 00 0 5 5 ID Budget ($000) 40 32 48 18 28 40 206 A B D E F Total Cumulative 0 4 2 6 4 5 D 0 5 5 5 E 2 7 3 8 2 10 10 0 10 8 2 10 3 4 18 14 18 32 50 1 2 10 10 10 10 8 4 8 4 18 14 10 F 12 0 0 10 2 12 8 9 5 00 6 7 8 12 12 12 12 8 8 12 20 20 20 26 22 26 2 6 20 20 64 84 110 132 158 160 166 186 206 LEGEND 6 ES ID EF SL SL LS DUR LF 10 11 12 Status Report: Ending Period 2 Task A B Cumulative Totals Status Report: Ending Period 4 Task A B Cumulative Totals Status Report: Ending Perlod 6 Task A B D E Cumulative Totals Status Report: Ending Period 8 Task A B D E Cumulative Totals Performance Indexes Summary Period EV 2 4 6 8 EAC, % Complete 75% 50% % Complete 100% 100% % Complote 100% 100% 75% 0% 50% % Complote 100% 100% 100% 33% 100% AC VAC, EV - EV | | | | - ||||| EV PV AC 25 12 37 AC 35 24 59 AC 35 24 24 0 10 93 AC 35 24 32 20 20 131 SPI PV PV PV - PV 5|||| CV ($000) ($000) 5||| CV SV ($000) SV SV ($000) SV PCIBStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started