Given the following sequence of activities, find the activities on critical path and length of critical path. Activity Predecessor Time ( days ) A -

Given the following sequence of activities, find the activities on critical path and length of critical path.
Activity Predecessor Time (days)
A ---5
B A 2
C A 4
D B 5
E B 5
F C 5
G E,F 2
H D 3
I G,H 5
Question 3 options:
A-C-E-G-I, 19 days
A-C-F-G-I, 21 days
A-C-F-H-I, 22 days
A-D-F-G-I, 23 day

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel,

7th Edition

470226218, 978-0470226216

More Books

Students also viewed these General Management questions