Given the following table, which project should you select using the weighted scoring model? Project 1 90 Project 2 50 Project 3 100 Project 4
Given the following table, which project should you select using the weighted scoring model? Project 1 90 Project 2 50 Project 3 100 Project 4 20 40 Project 5 0 90 20 30 Criteria Supports key objectives Strong customer demand Low risk Profitability potential Competitive advantage Weight 10% 20% 10% 30% 30% 100 100 10 50 30 60 10 50 30 40 50 90 50 40 10 90 Select one: a. Project 1 b. Project 2 c. Project 3 d. Project 4 e. Project 5