Question: Given the following three jobs (processes), determine the order in which processes will complete assuming FCFS scheduling. Process Arrival Time CPU Burst time Priority P1

Given the following three jobs (processes), determine the order in which processes will complete assuming FCFS scheduling.

Process Arrival Time CPU Burst time Priority

P1 5 10 2

P2 15 5 1

P3 0 20 3

a.) P1, P2, P3

b.) P1, P3, P2

c.) P2, P1, P3

d.) P2, P3, P1

e.) P3, P1, P2

f.) P3, P2, P1