Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time (te) estimate? Question 19Select
Given the following time estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the expected time (te) estimate? Question 19Select one: a. 6 days b. 4 days c. 3 days d. 4.5 days e. 1 week, not counting weekends
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started