Given the following times for the activities, compute the variance for activity B: Activity Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A
Given the following times for the activities, compute the variance for activity B: Activity Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A 5 6 7 B 1 3 5 C 1 2 4 D 2 4 6 0.44 0.66 [(3 1) / 6] [(5 1) / 6]