Given the information below, how long is the Critical Path? table[[Activity,Time,table[[Immediate],[Predecessor]]],[A,2,---],[B,1,---],[C,5,A],[D,4,B],[E,7,C, D],[F,2,E],[G,9,F],[H,6,F],[I,5,D H],[S
Given the information below, how long is the Critical Path? \table[[Activity,Time,\table[[Immediate],[Predecessor]]],[A,2,---],[B,1,---],[C,5,A],[D,4,B],[E,7,C, D],[F,2,E],[G,9,F],[H,6,F],[I,5,D H],[S