Question
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the
Given the information below: (Use normal time to calculate original path)
a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days?
b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days?
c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from20 to19 days?
d) What is the total cost to reduce the project from the original normal completion time to 19 days?
Activity Immediate Predecessors Normal time Crash time Normal cost Crash cost
A - 5 3 $3,000 $3,600
B - 6 4 $3,500 $4,300
C A 7 5 $3,300 $4,000
D B 5 4 $2,200 $2,400
E B 3 2 $1,700 $2,200
F D, E 5 3 $2,200 $3,600
G C,D 7 6 $1,900 $2,550
H F,G 3 2 $1,200 $1,750
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started