Given the portion of the network shown below, what is the earliest finish time for activity F, if the earliest start time of A is
Given the portion of the network shown below, what is the earliest finish time for activity F, if the earliest start time of A is 8 and the earliest start time of B is 11 ? A) 4 B) 15 C) 31 D) None of these