Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4

Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8.

Time Period
Task DUR ES LF SL Budget (PV) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 2 0 2 0 420 200 220
B 6 2 8 0 2500 200 700 200 600 200 600
C 5 2 9 2 1490 200 400 500 90 300
D 4 8 12 0 1560 360 400 400 400
E 3 7 12 2 1000 400 400 200
F 3 12 15 0 610 200 110 300
Period PV total 200 220 400 1,100 700 690 500 1,000 760 600 400 400 200 110 300
Cumulative PV total 200 420 820 1,920 2,620 3,310 3,810 4,810 5,570 6,170 6,570 6,970 7,170 7,280 7,580

(Do not round intermediate calculations. Round your table answer entries to the nearest whole number.)

End of Period 4
Task Actual % Complete EV AC PV CV SV
A Finished 500
B 60 1,000
C 35 600
D 0 0
E 0
Cumulative Totals

End of Period 8
Task Actual % Complete EV AC PV CV SV
A Finished 500
B Finished 2,200
C Finished 1,500
D 25 400
E 35 500
F 0 0
Cumulative Totals

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Finance

Authors: Keith Pilbeam

2nd Edition

0333730976, 978-0333730973

More Books

Students also viewed these Finance questions

Question

What are the HRM implications of this type of merger?

Answered: 1 week ago

Question

What is an RPIC, and where was it required?

Answered: 1 week ago