Answered step by step
Verified Expert Solution
Question
1 Approved Answer
Given the schedule and time for completion of a project: Immediately Preceding Hours needed to perform the task Task 1 2 3 4 5
Given the schedule and time for completion of a project: Immediately Preceding Hours needed to perform the task Task 1 2 3 4 5 6 7 8 9 1 1 2 2,3 4 2,3 4,5 6,7,8 Tasks 9 7 4 5 7 3 2 4 6 (1) Draw PERT diagram (2) Find the Critical path to complete the project (3) What is the minimal number of hours needed to complete the project?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
1 PERT Diagram 9hrs 9hrs 7hrs 2 Critical Path is ...
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started