Given the two projects with given cash flows, the NPV of project A is how many more (or less use the negative sign if less)
Given the two projects with given cash flows, the NPV of project A is how many more (or less use the negative sign if less) dollars than project B if the discount rate is 9%?
Answer with two decimals.
Project A Project B
CF0: -13,164
CF1: 3,200
CF2: 4,270
CF3: 9,704
CF4: 6,066
CF5: 2,829
CF0: -13,164 -10,193
CF1: 3,200 1,694
CF2: 4,270 2,814
CF3: 9,704 4,698
CF4: 11,385 8,013
CF5: 2,829 13,630